140 Tesla Megapacks on a Shiga Hillside: One of Japan’s Biggest Grid Batteries Switches On Dec. 1

One of Japan’s biggest grid batteries is about to go to work, and it’s built from Tesla Megapacks. ORIX said on Nov. 24 that its Maibara Koto battery station (米原湖東蓄電所) in Maibara, Shiga Prefecture, starts commercial operation on Monday, Dec. 1. The site holds 140 lithium-ion battery containers rated at 134 megawatts and 548 megawatt-hours, which ORIX’s announcement calls one of the largest in Japan by its own count.

ORIX’s release doesn’t name the hardware. Tesla did that itself back on Feb. 4, 2025, when Tesla Japan announced that Megapack had been chosen for the exact same 134 MW / 548 MWh project, and the Kyoto Shimbun headlined this week’s story with the rows of “U.S. Tesla-made containers” now sitting on the site.

There’s a small detail in there worth noticing. In that 2025 announcement, Tesla Japan said the station was scheduled to start operating in 2027. It’s opening on Dec. 1, 2026.

What the two numbers mean

Battery plants are described with two figures, and they measure different things. Megawatts (MW) is how much power the plant can push into the grid at once, like the width of a pipe. Megawatt-hours (MWh) is how much energy it can store in total, like the size of the tank. Divide 548 by 134 and you get roughly four hours: Maibara can run flat out for about four hours before it’s empty.

ORIX puts that in household terms. One full charge and discharge equals the daily electricity use of about 51,000 Japanese homes, using a Ministry of the Environment figure of about 10.7 kWh per household per day. That’s a way to show the size, not a count of homes it supplies.

The job is simple to describe. The plant soaks up electricity when there’s more than the grid needs (a sunny spring afternoon, say) and sends it back when demand climbs or the sun goes down. According to Nikkei, it will mainly charge from the Kansai Electric Power service area and discharge back into it.

Why a 20-year auction matters more than the ribbon cutting

The Dec. 1 start is commercial operation. The bigger date is April 2027, when the station begins running under Japan’s long-term decarbonization power auction (長期脱炭素電源オークション). That program, run through the grid coordinator OCCTO, pays winning projects revenue that covers their fixed costs, in principle for 20 years. For a battery owner, that turns a bet on volatile power prices into something a bank can lend against.

Maibara wasn’t a small winner. Tesla Japan said in 2025 that it had the largest awarded capacity of any battery project in the auction’s first round, for fiscal 2023, and energy news site Enehub reported it was one of 30 battery projects awarded that year, with Toshiba Plant Systems handling engineering and construction.

The local paper filled in the rest. The Shiga Yukan reports that the roughly 25,000-square-meter site sits on city-owned land in Maibara’s Banba district, leased to ORIX until March 2047 for ¥6.48 million a year (about $40,700). It connects to the grid through Kansai Transmission and Distribution’s Koto substation next door, with 35 intermediate transformers and three extra-high-voltage transformers on site. There’s also a public plaza and a biotope pond, with signs for kids learning about renewable energy. (A grid battery with a nature walk is a very Japanese way to do infrastructure.)

Not the only Megapack switching on this month

Maibara is the second large Megapack project in Japan to start operating in November. On Nov. 15, a roughly 30 MW / 125 MWh Megapack system began commercial operation beside a 39 MW solar farm in Oita City, according to Toshiba, which built it, and Osaka Gas, which runs the trading. That one is owned with solar developer Sonnedix, and it exists to fix a very Kyushu problem: on bright spring and autumn days the island makes so much solar power that utilities order plants to throttle output (出力制御, “output curtailment”). The battery stores that midday surplus and sells it in the evening instead.

Put the two together and Tesla has added roughly 673 MWh of grid storage in Japan in a little over two weeks. For scale, Tesla deployed 13.7 GWh of storage worldwide in the third quarter, according to its Q3 production and deployment report. Maibara alone is about 4% of that quarter. In Japan, it’s a landmark. On Tesla’s global tally, it’s about half a week of deployments.

The EVX Take

Most Japanese drivers know Tesla as the company whose cars they see in Tokyo and whose FSD they still can’t use here. Megapack is the part of Tesla that is already fully licensed, plugged in and earning in Japan, and it’s growing quietly. The auction system is the reason: 20 years of predictable revenue makes grid batteries an infrastructure investment instead of a trading bet, and that pulls in owners like ORIX, Osaka Gas and Toshiba, the kind of names Japanese utilities trust. That’s also a market Japanese companies want, so every American container on a Shiga hillside is a data point in a real competition. The detail we like best is the calendar. A project Tesla Japan once penciled in for 2027 is switching on with a month to spare in 2026.

If you’d rather have a smaller version at home, Tesla Japan is currently pitching Powerwall 3 for snow country, saying it’s rated down to -20°C. Earlier EVX coverage of Tesla’s energy business: its Powercore solid-state transformer for data centers and its $3.1 billion plan to refine its own solar silicon in Texas.

Sources: ORIX (Nov. 24, 2026), Tesla Japan (Feb. 4, 2025), Nikkei, Kyoto Shimbun, Shiga Yukan, Enehub, TeslaNorth, Toshiba, Osaka Gas, Tesla Q3 2026 deployment report (SEC).

Image: Rendering of the Maibara Koto battery station with its Megapack rows, from Tesla Japan’s Feb. 4, 2025 press release (cropped).

Follow @teslaloha on X for more

Related articles

CATL’s New 30# Chocolate Battery Packs 100 kWh Into a 99-Second Swap, With Huawei on Stage

CATL unveiled the 30# Chocolate swap battery: 100 kWh, 700+ km CLTC, 600 kW and a 99-second swap or a 10-minute fast charge. Who might use it, what Huawei announced, and why it matters for Japanese brands in China.

Japan’s Carmakers Bring Chinese Brains to the Guangzhou Auto Show, and Nissan Wants to Ship Them Home

At the 2026 Guangzhou Auto Show, Lexus debuted the TZ EV, Toyota named its first range-extender with Huawei and CATL tech, and Nissan launched the NX7 PHEV, a day after reports that Nissan will import China-built PHEVs to Japan.

Tesla 2026.44.3.1 Gives You a ‘Warm Up the Battery’ Button, Just in Time for Winter

Tesla's 2026.44.3.1 update adds manual battery preconditioning in the car and app, so you can warm the pack for a fast charge without navigating to a Supercharger. Why it matters for Japan's small Superchargers and CHAdeMO stops.

Stock Watch: Tesla Rings Up Exactly $400.00 in a Black Friday Half-Day as Harmonic Drive Leads Tokyo Up 8.46%

Tesla closed at exactly $400.00 (+5.22%) in Friday's 1 PM half-day, SpaceX added 4.83%, and Harmonic Drive led a broad Tokyo rally with an 8.46% jump.

Suzuki’s Kei EV Hit the Gym for Europe: Meet the Electric Ignis, Due Summer 2027

Suzuki unveiled the all-new Ignis, its first global compact EV: Japan's e SKY kei car stretched for Europe, with a 26 kWh LFP battery, 67 kW motor and 1,080 kg curb weight. It goes on sale from summer 2027. The specs, the range question, and why it's Japan's answer to cheap Chinese EVs.
EVX News Desk
EVX News Deskhttps://evxnews.com
The EVX News Desk is the newsroom of EVX News, an independent, Japan-based site covering Tesla, SpaceX, Starlink, xAI, AI, robotics and the wider EV industry in English and Japanese. The desk pays special attention to Japan and China: the Japanese market and automakers, charging and policy in Japan, and China's fast-moving EV makers such as BYD, including the weekly Japan & China EV Week digest. We don't race to be first. Every Desk story is checked against multiple reputable sources before publication, links to primary sources wherever possible, and runs under our Editorial Policy, overseen by founder and editor Lester Miyashiro. Spot an error? Tell us via our Contact page and we will review it and correct it promptly.

Leave A Reply

Please enter your comment!
Please enter your name here