Elon Musk’s Terafab chip project has started shopping for equipment in Japan, and it isn’t asking for the usual lead times. Several Terafab procurement officials visited Japan earlier this month and met with local chipmaking-equipment suppliers, Nikkei reported on Monday, Nov. 9, and some of the tools they asked for are due in just a few months.
One equipment maker told the paper the request was unreasonable, then said it would do as much as it could anyway. Another supplier executive summed up the mood: the biggest talking point in the chip industry right now isn’t Kioxia or Rapidus, it’s Elon Musk. Nikkei’s English-language edition, Nikkei Asia, followed on Tuesday with the same picture of excitement mixed with bewilderment.
What the report doesn’t include matters too. Neither Terafab nor any supplier has named the companies involved, and there’s no public detail on which tools were ordered or how many. Tesla, SpaceX and the Japanese equipment makers haven’t announced anything.
The 1-million-wafer target
The scale is the eye-opener. According to Nikkei, Terafab informally told equipment makers this fall that it wants to reach 1 million wafers a month sometime after 2032. About 700,000 of those would be memory chips and at least 300,000 would be logic chips for computing. Nikkei compared that with the 25,000 wafers a month at the plant Rapidus built in Chitose, Hokkaido, Japan’s national bet on leading-edge chips. That works out to roughly 40 Rapiduses.
Terafab is a joint Tesla and SpaceX project. The goal is to make chips in-house for Tesla’s self-driving cars and Optimus robots, plus SpaceX’s planned space-based AI data centers, with design, fabrication, packaging and testing all on one site. It’s being built in two steps. A research fab in Austin comes first. The volume plant goes up in Grimes County, northwest of Houston, where the Texas governor’s office announced in August a first phase worth more than $16.8 billion with 3,000 jobs, backed by a $30 million Texas Enterprise Fund grant.
Why the deadlines are so short
The rush follows the schedule Musk set out in October. On Tesla’s third-quarter call, the company said the Austin fab was under construction with equipment commissioning planned for 2027 (our Q3 earnings recap has the details). Musk is aiming for a first working test chip at the research fab around May or June 2027 and mass production in the second half of 2028, a timeline he has called very aggressive himself. On SpaceX’s own earnings call, he thanked ASML and other partners for pulling equipment delivery dates forward (we covered that call here).
Plenty of people in the industry are skeptical, and Nikkei didn’t hide it. A leading-edge fab usually takes three years or more from planning to volume production. Even after the tools are in, it takes months to get defect rates down to where output is reliable. Hisaya Suzuki of the research firm Omdia told Nikkei that with SpaceX’s chip demand still hard to gauge, it remains to be seen whether the plant can fill its capacity once it’s built.
Terafab isn’t starting from zero on process know-how. Intel said in April that it would work with the project on chip design, manufacturing and packaging, and Nikkei says talks with TSMC are ongoing, though TSMC’s role hasn’t been decided. The chips matter to Tesla’s whole roadmap. AI5 is due inside Optimus by around April 2027, Tesla said in October, and Musk has argued that Samsung, TSMC and Micron can’t add capacity fast enough for what Tesla and SpaceX have planned.
The silence from Terafab itself fits the pattern. Musk talks about the target in public and lets suppliers work out what it means for their factory schedules. This time a lot of those suppliers are in Japan.
The EVX Take
This is the clearest sign yet that Musk’s chip ambitions will run through Japanese factories as well as Taiwanese and Korean ones. Japan leads several process steps a fab can’t skip: Tokyo Electron in coater/developers and etch, SCREEN in wafer cleaning, Advantest in chip testers, Lasertec in mask inspection. Nikkei didn’t say who got the orders, so treat any name as a guess until someone confirms it. The real tension is capacity. Those order books are already crowded with AI-driven work for TSMC, Samsung and the memory makers, so a new customer demanding delivery within months forces a choice about who waits. If Terafab gets anywhere near 1 million wafers a month, it would be a far bigger buyer of Japanese tools than Rapidus plans to be. That’s a strange thought for Japan’s chip policy, which has spent years funding a domestic champion while the biggest new customer turns out to be a carmaker and a rocket company from Texas.
Sources: Nikkei (Nov. 9) and Nikkei Asia (Nov. 10); Financial News and ChosunBiz, both reporting on the Nikkei article; Office of the Texas Governor (Grimes County Terafab, Aug. 6); Texas project announcements; Tesla and SpaceX Q3 2026 earnings calls.
— The EVX News team